Creating Holidays/Closings
This lesson will demonstrate the steps required to set up the days the facility will be closed.
First Click Tools > Manage Facilities, to access the "Facility Manager" dialog.
Open the facility
![Open the facility](https://media.screensteps.com/image_assets/assets/006/029/612/original/Open%20the%20facility..png)
1. Select the Facility.
2. Click Edit.
Click Scheduler
![Click Scheduler](https://media.screensteps.com/image_assets/assets/006/029/614/original/media_1298319736062.png)
Click the Scheduler Tab.
Create Facility Closings
![Create Facility Closings](https://media.screensteps.com/image_assets/assets/006/029/616/original/Create%20Facility%20Closings..png)
1. Click the Add Closing button.
Edit the Day
![Edit the Day](https://media.screensteps.com/image_assets/assets/006/029/618/original/Edit%20the%20day..png)
1. Enter the Name of the closing.
2. Enter the Start and End Dates of the closing.
3. Click OK to save.
Update the Schedule
![Update the Schedule](https://media.screensteps.com/image_assets/assets/006/029/620/original/Update%20the%20Schedule..png)
Click the Update button to update the Schedule.